In December 2016, the Apis Cor company in cooperation with PIK proceeded to print the building using a mobile 3D printer. Construction took place at the Apis Cor company’s test facility in the town of Stupino, on the territory of the Stupino aerated concrete factory. Printing of self-bearing walls, partitions and building envelope were done in less than a day: pure machine time of printing amounted to 24 hours.